Revision 55598a8...
Go back to digest for 23rd January 2011Features in Office
              Dag Andersen committed changes in [calligra] /:  
              
                
              
plan: scheduling optimization
Add Calendar::firstAvailableBefore() to methods that needs special timezone treatment.
Fix a couple of bugs in calendar.
Add timezone definition to unit tests as calendars cannot work without them anylonger.    
File Changes
Modified  8 files  
                
                - kplato/libs/kernel/kptcalendar.cpp
- kplato/libs/kernel/kptcalendar.h
- kplato/libs/kernel/tests/CalendarTester.cpp
- kplato/libs/kernel/tests/CalendarTester.h
- kplato/libs/kernel/tests/DateTimeTester.h
- kplato/libs/kernel/tests/debug.cpp
- kplato/plugins/schedulers/rcps/tests/ProjectTester.cpp
- kplato/plugins/schedulers/rcps/tests/ProjectTester.h
8 files changed in total  
               KDE Commit-Digest